The banking business moved its 560 staff from its former base at Mays Meadow to Belfast Harbour’s 16-storey tower.
Santander took 27,000 sq ft across two floors at City Quays 3 following a 20 week refit programme.
This project consisted of the supply and installation of the complete mechanical services installations including LTHW and CHW, 4 Pipe Fan Coil Units, Ventilation, Domestic, Drainage, BMS, Water Leak Detection, etc.
The M&E services were semi exposed therefore coordination with sprinkler, lighting, architectural/ acoustic features, etc was essential. We provided full coordination of MEP.